Allowances in a Construction Estimate: How to Write Them So Nobody Is Surprised

Updated

Example project photo.

An allowance lets you give a homeowner a price before every selection is made. It’s one of the most useful lines in a remodeling estimate, and one of the most misunderstood. Written well, it keeps the job moving. Written badly, it’s the line the homeowner feels misled by at the end.

What is an allowance in a construction estimate?

An allowance is a set amount in your price for an item the homeowner hasn’t chosen yet: tile, cabinets, a vanity, light fixtures, appliances. When they pick, the price goes up or down by the difference between the allowance and what they chose.

Example: the estimate includes a $2,500 allowance for the vanity and countertop. They choose one that costs $3,200. The price goes up $700. They choose one that costs $2,100. The price goes down $400.

That’s it. The trouble comes from everything the line leaves unsaid.

Allowance for cabinets and hardware: $14,000

Right on the allowance. No change.

Total $55,500

When to use an allowance

Use one when the homeowner needs your price before they’ve made a selection, and the selection could reasonably swing the cost. Common allowances in residential work:

  • Tile (per square foot or as a total)
  • Cabinets
  • Countertops
  • Plumbing fixtures (vanity, faucets, tub, toilet)
  • Light fixtures
  • Appliances
  • Flooring material
  • Hardware

Don’t use an allowance for something you can price now. If the homeowner already picked the faucet, price the faucet.

Set an amount that matches their taste, not your bid

The fastest way to lose a homeowner’s trust is a low allowance that makes your total look competitive and then blows up at selection time. Set allowances from what this homeowner is likely to pick:

  • Listen at the walkthrough. Did they show you photos? Mention a brand? Point to the neighbor’s kitchen? That’s your allowance.
  • Price it from real stores. Check what the kind of product they described actually costs at the supplier you’d use.
  • Round up slightly, not down. A selection that comes in under the allowance is a pleasant surprise. One that comes in over is a hard conversation.

The low allowance trap

Estimate A

  • Cabinet allowance$9,000
  • Tile allowance$600
  • Lighting allowance$400

Total$52,000

Estimate B

  • Cabinet allowance$14,000
  • Tile allowance$1,200
  • Lighting allowance$900

Total$55,500

Example numbers.

Say exactly what the allowance covers

The single most important sentence: is installation in the allowance or in your price? Then cover the rest:

  • Material only, or material and labor. Most contractors keep installation in their price and the allowance covers material only. Say which.
  • How it’s measured. A total ($1,200 for backsplash tile) or a unit price ($6 per square foot for 200 square feet).
  • What happens over and under. The difference goes on the price either way. Say whether savings come back as a credit.
  • Your markup on overages. If you add your markup to the difference, say so up front. If you don’t, say that too.
  • When the selection is due. A late selection can stall the schedule. Give a date or a milestone.

Backsplash tile:

Example allowance wording

Adapt these to how you price. They’re examples, not contract terms.

Vanity and countertop

The price includes a $2,500 allowance for the vanity and countertop. If your selections come in above or below that, the price changes by the difference. Installation is already in the price.

Backsplash tile

Backsplash tile: $1,200 allowance for material, about 40 square feet. Installation, grout and edge trim are in the price. If the tile you pick costs more or less, the price changes by the difference. Please confirm your selection before cabinet installation.

Cabinets

Cabinets: $14,000 allowance for the cabinets and hardware, delivered. Installation is in the price. Selections are due before we order, at least six weeks before the start date.

Light fixtures

Light fixtures: $900 allowance for the five fixtures shown on the plan. We install the fixtures you choose. Changes to the number or location of fixtures are priced separately.

Flooring

Flooring material: $5 per square foot allowance for 320 square feet ($1,600). Prep and installation are in the price. If your selection costs more or less per square foot, the price changes by the difference.

Show the math when selections come in

When the homeowner chooses, put the change in writing before you order: the allowance, the actual cost, the difference, and the new total. One short note, approved by the homeowner, keeps the final payment from becoming a surprise. Some contractors give the homeowner a simple list of every allowance, its amount and its due date, so they can track their own choices.

AllowanceAmountDuePickedDifference
Cabinets$14,000Six weeks before the start date
Countertops$4,500Before cabinet installation
Backsplash tile$1,200Before cabinet installation
Light fixtures$900Before the wiring starts

Change to the total: Nothing picked yet.

Example only. Nothing is saved.

One short note, approved before you order.

Allowances and the rest of the estimate

An allowance works best when the rest of the estimate is just as clear: a scope in parts, a price for each part, and a “Not included” section that says what the homeowner is supplying. See:

Get Workbencher

Good work deserves a great pitch.

In Workbencher, mark any line as an allowance and the homeowner sees it labeled, with a plain note that allowances are budgets for their selections. You set every price. Create your first proposal today.

Common questions

Is an allowance the maximum the homeowner will pay?

No. An allowance is a placeholder, not a cap. If the selection costs more, the price goes up by the difference. Say that plainly in the estimate.

Do homeowners get money back if they spend less?

They should, and your estimate should say so. “The price changes by the difference” covers both directions.

Should installation be included in an allowance?

Most contractors keep installation in their own price and use the allowance for material only. That way a pricier tile doesn’t quietly change your labor. Either way, say which.

Can I add markup to an allowance overage?

Many contractors do. If you do, say so in the estimate before the homeowner starts picking.